Question : How long will it take to complete a small, bathroom remodel?
Hi all,
I must preface this question with “we only have one bathroom”, so time is of the essense.
Here’s what we want done:
– New shower/tub insert
- New tile on floor and half way up walls (sorry – not sure what that’s called)
- Repair water damage (there’s a leak in tub area – it’s been going on for about 6 months)
- New cabinet (will order)
- Paint as needed (will keep current color)
- Replace fixtures
- Update plumbing (I think this will be limited)
Other than the water damage, I don’t think we’ll have to replace/remove any sheetrock. Also, we’re keeping the toilet (just replaced).
So, how long do you think this will take and is there any wisdom that you’d like to pass along. We’re open to all suggestions. We’ll be using a friend’s bathroom until all is done, but we want it done fast!
Thanks!
small bathroom remodel
Best answer:
Answer by Richard M
This remodel can be done in 12 working days minimum. The scheduling can be quicker if no sub contractors are involved.
If you have moderate skills and are doing the work yourself, I’d say 2 weeks. But then again, the remodeler’s rule of thumb is to add 50% extra time, and double the budgeted expense. As you get into your project, you’ll probably note that to be so very true…